As we continue to move the ball up the hill, this is the rough timeline for us to reach the "top":
Complete design development | now - 2/15 |
Obtain preliminary costing | 3/1 |
NYC Building Depart Submission | 3/15 |
Foundation/First Floor Construction | 5/15 - 8/1 |
Module (floors 2-4) Fabrication | 5/15 - 8/1 |
Set Modules on Foundation/First Floor | 8/1 - 8/3 |
Interior/Exterior Finishing | 8/3 - 10/1 |
Certificate of Occupancy/Move - In | 10/1 |
As we look back, the current timeline has us about sixty days behind our original thinking. The complexity of balancing conservation/generation with design has driven many iterations of the design, but at this point it seems all elements are in check. I am so excited about how this is progressing, what do you think, love to hear from you with thoughts and questions.
BTW, check out new coverage from Metro's International Edition "Adding To It's Appeal" an article about our role in Red Hook's evolution.
No comments:
Post a Comment